160 tn transformer transport in Estonia
Year of Publication:
Categories:
- Route and project planning |
- Special transport |
Silvasti transported 160 tn transformer in Estonia from Sindi (Pärnu area) to Tsirguliina (Valga area). Route was approx. 230 km and transformer were transported by 4-axle truck and with 18-axle modular trailer.
Route was partly very tight small roads, where this 36-meter combination was just able to move. Route had also few weak bridges, why it was decided already in the planning phase to add some axles to the trailer. By doing this, the weight load divided more equally, and axle weights were lowered.